Construction & land use · No. 1
Securing a Building Permit
PD 1096 also known as the Building Code of the Philippines has it in Section 301, Building Permit, “No person, firm, or corporation, including any agency or instrumentality of the government shall construct, alter, repair, convert, use, occupy, move, demolish, and add any building/structure or any portion thereof or cause the same to be done, without first obtaining a building permit therefore from the Building Official assigned in the place where the subject building/structure is located pr to be done.” All prescribed application forms (NBC Forms) are available and shall be used by the applicant. The permit becomes null and void if work does not commence within 1 year from the date of such permit, or if the building or work is suspended or abandoned at any time after it has been commenced for a period of 120 days.
- Processing time
- 2 days, 1 hours and 40 minutes
- Fees
- *Refer to The NEW SCHEDULE OF FEES AND OTHER CHARGES OF THE REVISED IMPLEMEN TING RULES AND REGULATI ONS (IRR) OF THE NATIONAL BUILDING CODE OF THE PHILIPPINE S (PD 1096) Penalties based on seriousnes s of violation
- Who may avail
- Any authorized individual, corporation, cooperative, etc. who is planning to construct within the Municipality of Pilar
- Transaction
- G2C · Complex
What to bring
Prepare these before you go.
For Lot Owners and Non-Owners:
Barangay Construction Permit (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itBarangay covering the area of construction
Locational Clearance (Notarized) (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itMunicipal Planning and Development Office
Latest Tax Receipt (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itOne-Stop-Shop (Copy of payment of RPT)
Tax Declaration (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itMunicipal Assessor’s Office
TCT, CLOA or any valid proof of ownership or Deed of Absolute Sale (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itLot Owner, Registry of Deeds
Application forms duly SIGNED & SEALED by a licensed Civil Engineer/Architect, Sanitary Engineer for Sanitary Plans & Electrical Engineer/Registered Electrical Engineer for Electrical Plans. Building plans duly signed and sealed by a licensed Civil Engineer/Architect and properly notarized (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itMunicipal Engineering Office, Internet Online
Lot plan signed and sealed by Geodetic Engineer (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itGeodetic Engineer
Structural design analysis signed and sealed by a Structural Engineer (when warranted) (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itStructural Engineer
Bill of Materials and Specification signed and sealed by Civil Engineer/Architect (Notarized) (5 Photocopies + 1 Photocopy if will be used for loan application) 10 10. Reproduced Photocopies of registration number and PTR of Engineers who signed in the plans (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itCivil Engineer, Architect Civil Engineer, Architect, Sanitary Engineer, Electrical Engineer, Master Plumber
Long hard brown envelope (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itVariety Store
Blueprint of building plans signed and sealed by Civil Engineer/Architect, Sanitary plans signed and sealed by Sanitary Engineer/Civil Engineer/Architect/Master Plumber, Electrical plans signed and sealed by Professional Electrical Engineer/Registered Electrical Engineer (5 Photocopies + 1 Photocopy if will be used for loan application) For Non-Owners: Additional
Where to get itCivil Engineer, Architect
Authorization letter from lot owner/s giving the applicant permission to build and construct on the property or Contract of Lease (5 Photocopies + 1 Photocopy if will be used for loan application)
Where to get itLot Owner
Photocopy of any valid ID of lot owner/s (5 Photocopies + 1 Photocopy if will be used for loan application) All requirements should be prepared in 5 building official to be assessed as to its with lacking documents. If Zoning Clearance Office) and a Fire Clearance (Bureau of Fire other documents indicated above are required official in 3 Photocopies. To facilitate processing, please take note of other requirements above:
- Requirements of the National Building
- Requirements of the Referral Codes [PEC], Revised Plumbing Code, Structural [PSME])
- Laws and Municipal Ordinances affecting
- Compliance with BP 344 (Accessibility commercial, institutional and public buildings
- If setback/yard requirements are not Firewall (strictly no opening) extending up provided. It shall be indicated on the site
- Grease Traps/Oil Separator shall be provided gasoline stations, auto repair shops,
- All revisions/additions made in the designer.
- Special Power of Attorney shall be application forms, plans and documents.
- All application forms and letters must information available.
- Forms and Letters, Plans, Specifications, pertinent documents must be signed owner.
Where to get itLot Owner NOTES: Photocopies and submitted to the office of the completeness. No application shall be processed (from the Municipal Planning and Development Protection) have been secured, the rest of the to be submitted to the office of the building the following before submitting the plans and Code of the Philippines PD 1096 (Architectural Code, Philippine Electrical Code Code [NSCP], Mechanical Engineering Code the design/project Law) shall be indicated in detail on plans for met on the sides and at the back/rear then a to at least 1 meter from the roof level shall be development plan with owner’s conformity. for hotels, restaurants, eateries, terminals, bakeries and other similar establishments. plans shall have an acknowledgement of the provided if the owner is not the signatory in all be properly filled-up with all the necessary Bill of Materials and Cost Estimates and other and sealed by the designer and signed by the
Steps
Submit all the required documents to the Municipal Engineering Office.
1.1 Assess the application.
1.2 Send to Mayor’s office for verification and pre-approval.
1.3 Inspect the location of the construction. Assess the value of building permit fee and its violation.
1.4 Issue the Order of Payment if the application is found to be complete and in order.
Proceed to One- Stop-Shop and pay the n ecessary fees.
2. Issue Official Receipt.
Receive the approved building permit.
4. Log and release the building permit to applicant.
Where to go
Municipal Hall, Pilar, Bataan
Municipal Hall line: (047) 643-4228
This office has no local number in the municipal office directory.
Original text from the Citizen’s Charter
1. Securing a Building Permit PD 1096 also known as the Building Code of the Philippines has it in Section 301, Building Permit, “No person, firm, or corporation, including any agency or instrumentality of the government shall construct, alter, repair, convert, use, occupy, move, demolish, and add any building/structure or any portion thereof or cause the same to be done, without first obtaining a building permit therefore from the Building Official assigned in the place where the subject building/structure is located pr to be done.” All prescribed application forms (NBC Forms) are available and shall be used by the applicant. The permit becomes null and void if work does not commence within 1 year from the date of such permit, or if the building or work is suspended or abandoned at any time after it has been commenced for a period of 120 days. Office or Division: Municipal Engineering Office Classification: Complex Type of Transaction: G2C – Government to Citizen Who may avail: Any authorized individual, corporation, cooperative, etc. who is planning to construct within the Municipality of Pilar CHECKLIST OF REQUIREMENTS WHERE TO SECURE For Lot Owners and Non-Owners: 1. Barangay Construction Permit (5 Barangay covering the area of construction Photocopies + 1 Photocopy if will be used for loan application) 2. Locational Clearance (Notarized) (5 Municipal Planning and Development Office Photocopies + 1 Photocopy if will be used for loan application) 3. Latest Tax Receipt (5 Photocopies + 1 One-Stop-Shop (Copy of payment of RPT) Photocopy if will be used for loan application) 4. Tax Declaration (5 Photocopies + 1 Municipal Assessor’s Office Photocopy if will be used for loan application) 5. TCT, CLOA or any valid proof of Lot Owner, Registry of Deeds ownership or Deed of Absolute Sale (5 Photocopies + 1 Photocopy if will be used for loan application) 6. Application forms duly SIGNED & Municipal Engineering Office, Internet Online SEALED by a licensed Civil Engineer/Architect, Sanitary Engineer for Sanitary Plans & Electrical Engineer/Registered Electrical Engineer for Electrical Plans. Building plans duly signed and sealed by a licensed Civil Engineer/Architect and properly notarized (5 Photocopies + 1 Photocopy if will be used for loan application) 7. Lot plan signed and sealed by Geodetic Geodetic Engineer Engineer (5 Photocopies + 1 Photocopy if will be used for loan application) 8. Structural design analysis signed and Structural Engineer sealed by a Structural Engineer (when warranted) (5 Photocopies + 1 Photocopy if will be used for loan application) 9. Bill of Materials and Specification signed Civil Engineer, Architect and sealed by Civil Engineer/Architect (Notarized) (5 Photocopies + 1 Photocopy if will be used for loan application) 10 10. Reproduced Photocopies of Civil Engineer, Architect, Sanitary Engineer, registration number and PTR of Engineers Electrical Engineer, Master Plumber who signed in the plans (5 Photocopies + 1 Photocopy if will be used for loan application) 11. Long hard brown envelope (5 Variety Store Photocopies + 1 Photocopy if will be used for loan application) 12. Blueprint of building plans signed and Civil Engineer, Architect sealed by Civil Engineer/Architect, Sanitary plans signed and sealed by Sanitary Engineer/Civil Engineer/Architect/Master Plumber, Electrical plans signed and sealed by Professional Electrical Engineer/Registered Electrical Engineer (5 Photocopies + 1 Photocopy if will be used for loan application) For Non-Owners: Additional 1. Authorization letter from lot owner/s Lot Owner giving the applicant permission to build and construct on the property or Contract of Lease (5 Photocopies + 1 Photocopy if will be used for loan application) 2. Photocopy of any valid ID of lot owner/s (5 Lot Owner Photocopies + 1 Photocopy if will be used for loan application) NOTES: All requirements should be prepared in 5 Photocopies and submitted to the office of the building official to be assessed as to its completeness. No application shall be processed with lacking documents. If Zoning Clearance (from the Municipal Planning and Development Office) and a Fire Clearance (Bureau of Fire Protection) have been secured, the rest of the other documents indicated above are required to be submitted to the office of the building official in 3 Photocopies. To facilitate processing, please take note of the following before submitting the plans and other requirements above: • Requirements of the National Building Code of the Philippines PD 1096 • Requirements of the Referral Codes (Architectural Code, Philippine Electrical Code [PEC], Revised Plumbing Code, Structural Code [NSCP], Mechanical Engineering Code [PSME]) • Laws and Municipal Ordinances affecting the design/project • Compliance with BP 344 (Accessibility Law) shall be indicated in detail on plans for commercial, institutional and public buildings • If setback/yard requirements are not met on the sides and at the back/rear then a Firewall (strictly no opening) extending up to at least 1 meter from the roof level shall be provided. It shall be indicated on the site development plan with owner’s conformity. • Grease Traps/Oil Separator shall be provided for hotels, restaurants, eateries, terminals, gasoline stations, auto repair shops, bakeries and other similar establishments. • All revisions/additions made in the plans shall have an acknowledgement of the designer. • Special Power of Attorney shall be provided if the owner is not the signatory in all application forms, plans and documents. • All application forms and letters must be properly filled-up with all the necessary information available. • Forms and Letters, Plans, Specifications, Bill of Materials and Cost Estimates and other pertinent documents must be signed and sealed by the designer and signed by the owner. FEES TO PROCESSING PERSON CLIENT STEPS AGENCY ACTIONS BE PAID TIME RESPONSIBLE 1. Submit all the 1.1 Assess the None 15 minutes Clerk II required documents to application. Office of the the Municipal Municipal Engineer Engineering Office. 1.2 Send to None 1 day Private Secretary Mayor’s office for II verification and Office of the Municipal Mayor pre-approval. 1.3 Inspect the None 1 day Engineer II location of the Office of the construction. Municipal Engineer Assess the value of building permit fee and its violation. 1.4 Issue the Order None 5 minutes Clerk II of Payment if the Office of the application is Municipal Engineer found to be complete and in order. 2. Proceed to One- 2. Issue Official *Refer to 10 minutes Clerk II Stop-Shop and pay the Receipt. The NEW Municipal n ecessary fees. SCHEDULE Treasurer’s Office OF FEES / One-Stop-Shop AND Windo w # 2 OTHER CHARGES OF THE REVISED IMPLEMEN TING RULES AND REGULATI ONS (IRR) OF THE NATIONAL BUILDING CODE OF THE PHILIPPINE S (PD 1096) Penalties based on seriousnes s of viola tion 3. Submit the official 3.1 Engineering None 1 hour Clerk II receipt to the staff processes the Office of the Municipal Engineering plans and pertinent Municipal Engineer Office. documents for final approval of Municipal the Municipal Engineer E ngineer. Office of the Municipal Engineer 4. Receive the 4. Log and release None 10 minutes Clerk II approved building the building permit Office of the permit. to applicant. Municipal Engi neer TOTAL: *Refer to 2 days, 1 The NEW hours and 40 SCHEDULE minutes OF FEES AND OTHER CHARGES OF THE REVISED IMPLEMEN TING RULES AND REGULATI ONS (IRR) OF THE NATIONAL BUILDING CODE OF THE PHILIPPINE S (PD 1096) Penalties based on seriousnes s of violation